Minister’s December Deadline Looms, Yet Gaibandha’s Tk 40 Crore Hospital Tower Stands Empty
Four years after a nine-storey building was handed over, its wards remain closed. Patients at the 100-bed Gaibandha General Hospital, which admits 200–300 people a day, are being treated on verandah floors.
When Health and Family Welfare Minister Sardar Md. Sakhawat Hossain made a surprise visit to Gaibandha General Hospital on 2 August, he promised that its new nine-storey building would be opened by December, complete with the necessary staff and medical equipment. With that deadline now days away, local people say there has been no visible progress.
Meanwhile, patients continue to be treated on verandah floors, under staircases and along corridors of the old hospital building. Critically ill patients who cannot get beds are also lying on the floor, while the new building stands next door.
Handed over in 2022, still not admitting patients
According to the Public Works Department, the district hospital was upgraded to 250 beds in 2014. In 2018, contractor The Engineers and Architects Limited was awarded the work order to construct a new hospital building at a cost of Tk 39.70 crore. The building was handed over to hospital authorities in early April 2022.
More than four years later, full inpatient services have yet to begin there. Only the ground floor is in use, housing the ticket counter, outpatient services, a pharmacist and a few other services. The upper floors, meant for admissions and full treatment, remain closed.
100 beds, up to 300 patients
Hospital authorities say that on average 200 to 300 patients are admitted every day against 100 beds. Doctors and nurses say a rise in seasonal illnesses has worsened the pressure. During visits on Monday and Tuesday, every ward was found holding several times its capacity, with patients and relatives so crowded together that doctors and nurses struggled to move.
Abdul Wares, from Bati village in Bonarpara union of Saghata upazila, was admitted with breathing difficulties last Tuesday and is being treated on the verandah floor. “There are no beds in such a big hospital,” said his son, Mominul Islam. “Keeping patients crammed together like this causes a lot of problems. The stench all around makes it hard to stay.”
“No visible steps”
Jahangir Kabir Tanu, convener of Gaibandha Samajik Sangram Parishad, said the minister had pledged to open the building by December with the required manpower and equipment, but alleged that no visible steps had been taken since.
No clear information has emerged on how many doctors and nurses have been recruited or posted since the minister’s assurance, or what stage equipment procurement has reached, deepening doubts over whether the promise will be kept.
55 doctors and 101 nurses needed
Hospital superintendent Dr. Md. Shahidullah said that, alongside medical equipment, 55 doctors, 101 nurses and staff for other posts are needed to run full services in the new building. He said letters had been sent to the relevant offices several times, and expressed hope that the building could be opened next month once these shortages are resolved.
Yet the need for staff and equipment was foreseeable from the day construction began. Why, then, were recruitment, postings and procurement not completed in the years since the building was handed over?
December will tell
The minister’s visit and pledge will mean something only when the new building’s doors open to patients. If people still have to lie on the floor despite a Tk 39.70 crore building next door, where is the benefit of that development? December will show whether the promise becomes reality or the building stays locked for longer still.